China firm drills East Africa’s longest tunnel

CHINA Communications Construction Co (CCCC) has drilled the longest railway tunnel in East Africa.

The tunnel is part of Phase 2A of the Standard Gauge Railway (SGR) that will run from the Kenyan capital city of Nairobi to Naivasha town.

An Aijun, general manager of SGR project head office at the CCCC, said on Monday that during the excavation, the project team overcame the challenges of water leaks, uneven pressure, shallow-depth excavation, surrounding rocks, structural fault-line and oil pipeline protection.

“With a total length of 4.5 kilometers, the Ngong tunnel is currently the longest tunnel in East Africa and the dominant work in SGR Phase 2A,” An said during celebrations to mark the breakthrough of the Ngong tunnel.

The Phase 2A, which extends for about 120km, is set to be completed in 2019. The Ngong tunnel has been designed as a single-track railway tunnel with a clearance height of 9 meters and a width of 7m.

CCCC engineers used the New Austrian Tunneling Method of drilling and blasting to build the tunnel and it is the first time that such a method has been used on such a large scale in Kenya.

The tunneling method is economical, efficient and has strong adaptability for different geological and groundwater conditions. The method is preferred because it controls surface collapse effectively and enhances the working environment during construction.

An said the construction team addressed the technical difficulty in designing and constructing in the Great Rift Valley to ensure a safe breakthrough of the tunnel, and this means the SGR Phase 2A has entered a new stage, laying a solid foundation for inauguration next year.

The general manager said that with quality as a foundation and safety as a lifeline, they shall maintain an all-round quality control system in the source, process, methodology and management, and enforce strict safety management at all procedures.

“We will continue to protect the environment, implement local contents and participate in social welfare, bringing real benefits to the local communities,” he added.

“Together with all our Kenyan partners, and building on what has been achieved at the FOCAC (Forum on China-Africa Cooperation) summit in Beijing, we shall construct a time-honored railway that will stand the test of time and operations, achieving greater success in a new era between our two nations,” he added.

According to Steve Zhao, spokesman for the CCCC Kenya SGR Project, 146 refuge holes of different sizes have been built within the tunnel to allow maintenance workers to take cover as the train approaches.

“There is one large refuge hole set up every 150 meters in the tunnel, and one small refuge hole set up every 30 meters in the tunnel,” Zhao explained.

A 533m-wide emergency rescue channel has also been built within the tunnel, to allow for vehicle access in case of emergencies.

Zhao said about 600 workers and engineers worked tirelessly overcoming all odds for 24 months to accomplish the engineering marvel.




 